Bitcoin mining tax in 2026 comes down to one restored rule: 100% bonus depreciation is permanent for US buyers, and qualifying ASIC miners acquired and placed in service after January 19, 2025 can be written off in full in the year they start hashing. The catch is timing — a miner only counts for your 2026 return if it is delivered, installed and hashing by December 31, 2026. An order, a deposit or a shipment in transit does not count. This guide explains the rule, the Section 179 alternative, and the year-end clock for in-stock versus pre-order hardware.
Bitcoin Mining Tax 2026: 100% Bonus Depreciation Is Back — Permanently
The One Big Beautiful Bill Act (OBBBA), signed into law on July 4, 2025, permanently restored 100% bonus depreciation. Section 70301 rewrote Section 168(k): for qualifying property acquired and placed in service after January 19, 2025, the first-year deduction is 100% — no phase-down, no sunset date. The old TCJA phase-down is repealed for property acquired after that cut-off. 2026 is the first full calendar year under the restored rule, reaffirmed by the IRS in Notice 2026-11 (January 2026).
What qualifies
Bonus depreciation covers tangible property with a MACRS recovery period of 20 years or less: machinery, equipment, computers, software. ASIC miners are equipment in that class — generally treated as 5-year property — and the same treatment extends to supporting farm gear: power distribution units, dry coolers, network switches and racking. Land, building structures and inventory never qualify.
The transition line
The January 19, 2025 cut-off is a hard line, and the acquisition date is the date of the binding written contract — not delivery, not payment. Property placed in service January 1–19, 2025 still falls under the old 40% rate; property acquired before January 20, 2025 and placed in service in 2026 gets the old 20% rate. A contract signed before January 20, 2025 can leave hardware on the old rates even if it starts hashing in 2026 — check the contract date, not the delivery date.
Section 179 vs Bonus Depreciation: Which One Fits a Mining Fleet
There are two ways to deduct a mining purchase in year one instead of spreading it over five years. Most buyers use bonus depreciation, but Section 179 has its place — and the two combine, Section 179 first, then bonus on the remainder.
| Section 179 | 100% bonus depreciation | |
|---|---|---|
| 2026 limit | $2,560,000 per year | No dollar cap |
| Phase-out | Reduced dollar-for-dollar once qualifying purchases exceed $4,090,000; eliminated at $6,650,000 | None |
| Income limit | Deduction capped at taxable business income | No income cap — can create a loss (excess business loss rules may apply) |
| Used equipment | Qualifies | Qualifies when bought from an unrelated party |
| What it covers | Qualifying equipment | Qualifying property with a recovery period of 20 years or less |
Which one fits your fleet
- A small fleet will often fit inside the Section 179 limit, which lets you pick which assets to expense.
- A container-scale purchase blows past the $2,560,000 limit fast — bonus depreciation has no cap, so it is the tool for large fleets.
- Buying used? Federal rules let used property qualify for bonus depreciation when bought from an unrelated party. MineForgeX sells 100% brand-new miners, so every unit we ship is new equipment on that test.
- Neither choice is automatic: the right split depends on your taxable income, your other equipment purchases and your state. Your CPA makes that call — this guide is general information, not tax advice.
What Counts as "Placed in Service" — and Why December 31, 2026 Is the Line
The deduction belongs to the year the asset is placed in service — delivered, installed and ready for its intended use. For an ASIC miner, that means racked, powered, connected to a pool and hashing. A deposit, a signed quote or a unit sitting in a shipping container does not count: the deadline is placed in service, not ordered.
How to prove the date
Keep the paper trail that fixes the placed-in-service date:
- The supplier invoice and the delivery receipt, with the delivery date.
- The install record: the date the unit was racked and powered.
- The first hashrate log or pool connection — the moment it started hashing.
- A photo of the racked unit with its serial number, dated.
The date is documented on Form 4562 with the tax return; if it is ever questioned, the delivery receipt plus the first pool connection is the evidence that decides it.
The December 31, 2026 line
To deduct a miner on your 2026 return, it must be placed in service by December 31, 2026 — ready and available for its intended use. As of November 18, 2026, that leaves 43 days. The deduction is still 100% in 2027, because the rule is permanent — but a miner that starts hashing in January 2027 is a 2027 deduction, a full year later. That is the whole reason to buy in-stock hardware now rather than a pre-order shipping next year.
What a 2026 Deduction Looks Like on Real Hardware
The arithmetic below is illustrative: real MineForgeX catalog prices, assuming qualifying business use under US federal rules. A deduction reduces taxable income — not a refund; its cash value depends on your tax position. This article makes no claim about mining revenue or payback; run that question in the Bitcoin mining profitability guide and the MineForgeX calculator.
| Fleet | Unit price | Fleet cost | First-year deduction at 100% |
|---|---|---|---|
| 10 x Antminer S21 Pro 234T | $3,490 | $34,900 | $34,900 |
| 20 x Antminer S23e Hyd 2U 865T | $9,529 | $190,580 | $190,580 |
| 5 x Antminer S23 Hyd 3U 1.16 PH/s | $30,000 | $150,000 | $150,000 |
| 50 x Antminer S23 Hyd 580T | $13,300 | $665,000 | $665,000 |
| 10 x Whatsminer M60S+ 210T | $2,880 | $28,800 | $28,800 |
Reading the table
- A 10-unit S21 Pro starter fleet costs $34,900 — all of it deductible in year one at 100% bonus depreciation.
- A 50-unit S23 Hyd fleet costs $665,000 — inside the Section 179 limit alone, but add containers, cooling and a second fleet in the same year and the $4,090,000 phase-out threshold comes fast. Bonus depreciation has no cap at all.
- Power, hosting, cooling and maintenance are separate deductions — operating costs, not part of the bonus depreciation calculation.
- Fleet cost is the hardware price. Freight, installation and electrical work may also qualify as part of the asset cost — confirm with your CPA how the invoice breaks those out.
The Year-End Clock: In-Stock Miners vs Pre-Orders
The December 31 deadline rewards hardware in stock today. A pre-order shipping in 2027 cannot be placed in service in 2026, however good the price.
In stock now
- Antminer S21 Pro 234T — $3,490, US warehouse ready.
- Whatsminer M60S+ 210T — $2,880, in stock with spot delivery.
- Antminer KS7 40T — $2,050, in stock with spot delivery.
- Antminer S23e Hyd 2U 865T — $9,529, limited allocation, available now.
- Antminer S23 Hyd 580T — $13,300, limited allocation.
- Antminer S23 Hyd 3U — $30,000, 1.16 PH/s at 9.5 J/TH, bulk order only: confirm the delivery date in writing before counting on a 2026 deduction.
A realistic year-end timeline
| Step | Target date |
|---|---|
| Order confirmed with delivery date in writing | By early December 2026 |
| Delivery, insured DDP from Houston or Frankfurt | Mid-December 2026 |
| Installed, powered and hashing | Before December 31, 2026 |
| Placed-in-service date documented (Form 4562) | With the 2026 return |
MineForgeX ships insured DDP from Houston and Frankfurt, and the delivery date is part of the quote — ask for it in writing, because the placed-in-service date depends on it. A November-shipping pre-order can still make the deadline if delivered and installed in December; a January-shipping pre-order cannot.
Records, Recapture and the State Question
Records to keep
Keep the invoice, delivery receipt, install date, first hashrate or pool-connection log, and the placed-in-service date on Form 4562. Years from now, the delivery receipt plus the first pool connection is the record that proves the deduction year.
Recapture
Selling or repurposing bonus-depreciated property early can trigger recapture tax — part of the deduction comes back as income. If you plan to resell miners within a few years, ask your CPA how recapture applies before you sell.
The state question
State tax conformity is not automatic: verify your state's treatment before assuming a full state deduction — California, for example, does not conform to federal bonus depreciation. The federal and state deductions are two separate questions.
Frequently Asked Questions
Is 100% bonus depreciation really permanent for Bitcoin miners?
Yes. The One Big Beautiful Bill Act (July 4, 2025) permanently restored 100% bonus depreciation under Section 168(k) for qualifying property acquired and placed in service after January 19, 2025. There is no sunset date and no phase-down, and ASIC miners qualify as tangible equipment with a recovery period of 20 years or less.
What does "placed in service" mean for an ASIC miner?
Delivered, installed and hashing — ready for its intended use. A miner counts for 2026 only if placed in service by December 31, 2026. An order, a deposit or a unit in transit does not count.
Can I deduct a miner I ordered but have not received yet?
Not for 2026. The deduction belongs to the year the miner is placed in service, so a miner that starts hashing in 2027 is a 2027 deduction. The 100% rule is permanent, so the deduction is still available — just a year later.
Should I use Section 179 or bonus depreciation for my fleet?
Section 179 suits smaller purchases: the 2026 limit is $2,560,000, it phases out above $4,090,000 of qualifying purchases, and it is capped at taxable business income. Bonus depreciation has no dollar cap and no income cap, so most large fleets use it — or Section 179 first, then bonus on the remainder. Your CPA decides which fits your return.
One clear next step: this article is general information, not tax advice. Pick the fleet size that fits your site, confirm the delivery date in writing, and take the quote to your CPA before December 31, 2026 — the deduction is permanent, but the tax year ends in 43 days.